Project Management Professional (PMP) Exam Practice – Question1797

You are working on a project to upgrade the existing fiber-optic cables in your province. You have determined that a resource can install 25 meters of cable per hour, so the duration required to install 1,000 meters would be 40 hours. This means you are
using______________


A.
Productivity efficiency factors
B. Parametric estimating
C. Analogous estimating
D. PERT

Correct Answer: B

Explanation:

Explanation:
Parametric estimating uses statistical relationships between historical data and other variables to calculate an estimate for activity parameters such as cost, budget, and duration. The activity durations then are determined quantitatively by multiplying the quantity
of work to be performed by the labor hours per unit of work. This technique can produce higher levels of accuracy depending on the reliability of the data in the model.