You are working on a project to upgrade the existing fiber-optic cables in your province. You have determined that a resource can install 25 meters of cable per hour, so the duration required to install 1,000 meters would be 40 hours. This means you are
using______________
A. Productivity efficiency factors
B. Parametric estimating
C. Analogous estimating
D. PERT
using______________
A. Productivity efficiency factors
B. Parametric estimating
C. Analogous estimating
D. PERT