Project Management Professional (PMP) Exam Practice – Question1818

Historical information is used______________


A.
To compare current performance with prospective lessons learned
B. To prepare the stakeholder management plan
C. To evaluate the skills and competencies of prospective team members
D. As an input to develop project charter

Correct Answer: D

Explanation:

Explanation:
Historical information is an organizational process access in the develop project charter process. Other organizational process assets are organizational standard processes, policies, and process definitions; templates from other project charters; and the lessons
learned data base.