Project Management Professional (PMP) Exam Practice – Question1862

One way to help mitigate personnel risks that may occur during the end of the project is to ______________


A.
Meet individually with each team member
B. Provide specific recognition to each team member who has worked on the project
C. Prepare a staff release plan
D. Document the time each person is to work on the project in a resource calendar

Correct Answer: C

Explanation:

Explanation:
The staff release plan determines the method and timing of releasing team members. Morale is improved if there are smooth transitions for the staff to upcoming projects. This staff release plan also helps to mitigate human resource risks that may occur. It is part
of the staffing management plan, which is part of the human resource plan.