Project Management Professional (PMP) Exam Practice – Question1864

Assume your project communication management plan has been approved by your sponsor and the members of your Steering Committee. You are managing a global project and have team members working virtually in four continents and stakeholders in
numerous locations. Your next step is to______________


A.
Set up an information management system
B. Select communications technology
C. Determine performance reporting methods
D. Select a communications model

Correct Answer: B

Explanation:

Explanation:
Although all four listed are tools and techniques in the manage communications process (another is communications methods), since this project is a virtual one, the choice of technology is an important consideration. It can vary from project to project and
throughout the life cycle, but as the project manager the focus is to ensure the choice is important for the information that is communicated.