Project Management Professional (PMP) Exam Practice – Question2021

The team implemented a risk response plan when a vendor was unable to fulfill a contract commitment for a training class. The response was to choose another vendor. However, in this type of training, it's hard to find a good company, and the one selected
doesn't have a much better reputation. The new company is somewhat better at meeting the terms of the contract, but still has some issues from time to time, which is no surprise. What best describes these issues?


A.
Secondary risk
B. Workaround
C. Residual risk
D. Risk response plan

Correct Answer: C