Project Management Professional (PMP) Exam Practice – Question2023

Crosswind Custom Homes is building a customer's dream house. However, rain has delayed the finish by two weeks. The Project Manager is evaluating options to make up the lost time. After discussing the various options with senior management, the Project
Manager has decided to fast track the project. By doing so, the Project Manager could be adding what to the project?


A.
Risk
B. Scope change
C. Responsibility
D. Time change

Correct Answer: A