You are beginning a new project staffed with a virtual team located across five countries. To help avoid conflict in work priorities among your team members and their functional managers, you ask the project sponsor to prepare a______________.
A. Memo to team members informing them that they work for you now
B. Project charter
C. Memo to the functional managers informing them that you have authority to direct their employees
D. Human resource management plan
A. Memo to team members informing them that they work for you now
B. Project charter
C. Memo to the functional managers informing them that you have authority to direct their employees
D. Human resource management plan