Project Management Professional (PMP) Exam Practice – Question2115

The close project or phase process addresses actions and activities concerning all of the following EXCEPT______________.


A.
Completion or exit criteria for the project or phase have been met
B. Stakeholder approval that the project has meet their requirements
C. Review of the project and/or phase information for potential future use
D. Documentation that completed deliverables have been accepted

Correct Answer: D

Explanation:

Explanation:
Documentation that the completed deliverables have been accepted is prepared as an output of validate scope. The close project or phase procedures provides a listing of necessary activities, including: confirmation that the project has met sponsor, customer,
and other stakeholder requirements; satisfaction and validation that the completion and exit criteria have been met; the transfer of deliverables to the next phase or to production/operations has been accomplished; and activities to collect, audit, and archive project
information and gather lessons learned have been addressed.