The close project or phase process addresses actions and activities concerning all of the following EXCEPT______________.
A. Completion or exit criteria for the project or phase have been met
B. Stakeholder approval that the project has meet their requirements
C. Review of the project and/or phase information for potential future use
D. Documentation that completed deliverables have been accepted
A. Completion or exit criteria for the project or phase have been met
B. Stakeholder approval that the project has meet their requirements
C. Review of the project and/or phase information for potential future use
D. Documentation that completed deliverables have been accepted