Project Management Professional (PMP) Exam Practice – Question2125

You are examining multiple scope change requests on a project you were asked to take over because the previous project manager decided to resign. To assess the degree to which the project scope will change, you need to compare the requests to which
project document?


A.
Preliminary scope statement
B. WBS
C. Change management plan
D. Scope management plan

Correct Answer: B

Explanation:

Explanation:
The WBS, along with the detailed scope statement and the WBS dictionary, defines the project’s scope baseline, which provides the basis for any changes that may occur on the project.