Project Management Professional (PMP) Exam Practice – Question1092

During project implementation, the project manager reviews identified key performance indicators (KPIs) and determines that the project is within budget and on schedule. To what process does this activity belong?


A.
Review Scope Baseline
B. Review Project Performance
C. Perform Integrated Change Control
D. Monitor and Control Project Work

Correct Answer: D

Project Management Professional (PMP) Exam Practice – Question1091

A projects primary focus is staying on schedule. To monitor this, the project manager requests monthly progress reports from the contractor.
What should the project manager ask the contractor to include in these reports?


A.
Gantt chart
B. Work breakdown structure (WBS)
C. Network chart
D. Schedule attributes

Correct Answer: A

Project Management Professional (PMP) Exam Practice – Question1088

A new product has been released. During testing, some defects were discovered and resolved, and a number of features were newly identified that would enhance the product.
What should the project manager do?


A.
Begin work on delivering these new features before closing the project.
B. Transfer ownership in accordance with the plan.
C. Implement a partial transfer of ownership while the additional work is being done.
D. Disregard the additional requirements.

Correct Answer: C

Project Management Professional (PMP) Exam Practice – Question1087

Due to a change in market conditions, the project sponsor insists on a scope change for a project that is scheduled for completion in a month. In addition, the sponsor requires that the same schedule be maintained.
What should the project manager do?


A.
Propose project crashing.
B. Seek formal approval from the change control board (CCB).
C. Discuss the issue with the stakeholders and modify the project management plan.
D. Meet with the project team for ideas on how to move forward and modify the project charter.

Correct Answer: B

Project Management Professional (PMP) Exam Practice – Question1086

A project is being audited, and the project manager receives numerous comments and questions from an unfamiliar person in the company. The project manager shares this information with team members, none of whom know this person. The project manager
is unsure how to manage this situation.

What should the project manager do first?


A.
Review the responsible, accountable, consult, and inform (RACI) matrix.
B. Respond to the persons comments and questions.
C. Check the stakeholder register.
D. Review the work breakdown structure (WBS).

Correct Answer: A