Project Management Professional (PMP) Exam Practice – Question1071

What is the critical chain method?


A.
A technique to calculate the theoretical early start and finish dates and late start and finish dates
B. A schedule network analysis technique that modifies the project schedule to account for limited resources
C. A schedule compression technique that analyzes cost and schedule trade-offs to determine how to obtain the greatest amount of compression for the least incremental cost
D. A technique to estimate project duration when there is a limited amount of detailed information about the project

Correct Answer: B

Project Management Professional (PMP) Exam Practice – Question1065

When a control chart is used to monitor performance of a process, which of the following will be set by the project manager and the appropriate stakeholders to reflect the point(s) at which corrective action will be taken to prevent exceeding the specification limits?


A.
Upper and lower control limits
B. Upper and lower specification limits
C. Process mean
D. Data points

Correct Answer: A