Project Management Professional (PMP) Exam Practice – Question1940

All of the following are true about a work breakdown structure (WBS) except?


A.
The team and the Project Manager should be involved in creating it
B. It will resemble an organizational chart in appearance when complete
C. The Activity Sequencing of the WBS can be done only in parallel
D. It is a decomposition of the work of the project

Correct Answer: C

Project Management Professional (PMP) Exam Practice – Question1939

There has been a great delay in waiting to get the charter approved. It's finally complete and you are assigned as the Project Manager. Senior management wants you to begin planning as soon as possible. If you are in the process of planning the project, what is
the best way to schedule Scope Verification?


A.
At the end of every phase on the project
B. After the sponsor defines what they want the project to create
C. When the project management plan is awaiting signoff
D. When the work of the project is done

Correct Answer: A

Project Management Professional (PMP) Exam Practice – Question1938

The sponsor on the airport runway project has just told the Project Manager about a change he wants. He says that the change will cost 20% less and should not cause any problems to the existing environment. Which of the following should concern the Project
Manager the most?


A.
Scope impact
B. Schedule impact
C. Quality impact
D. Scope and schedule impact

Correct Answer: D

Project Management Professional (PMP) Exam Practice – Question1937

The project team is involved in creating the work breakdown structure of the project. Which of the following best describes a work breakdown structure (WBS) that will be created?


A.
The work should be decomposed to a realistic level of detail
B. If the work is not listed in the WBS, it is not in the project
C. The accumulation of the work in the WBS should be equal to the work of the project
D. All of the answers

Correct Answer: D

Project Management Professional (PMP) Exam Practice – Question1936

A new manufacturing facility is being built for a consumer electronic company. The project to create it is nearing completion and will soon begin to enter the Closing phase. This will involve a number of people, but who will ultimately approve the work of the
project?


A.
Project Manager
B. The customer
C. Senior management
D. Stakeholders

Correct Answer: B

Project Management Professional (PMP) Exam Practice – Question1935

The Project Manager is working with the customer to gain formal acceptance on the documentation deliverables for a software project. The customer is saying that the deliverables are unusable in their present form as they don?t align with the project
requirements. Upon reviewing documentation, the customer tells the Project Manager that the requirements are not accurate, to meet the needs for which the project was undertaken. Which of the following will help fix this problem?


A.
Creating the work breakdown structure
B. Scope Control
C. Scope Definition
D. Scope Verification

Correct Answer: B

Project Management Professional (PMP) Exam Practice – Question1933

Project Scope Management is characterized by processes in the Planning, as well as Monitoring and Controlling phases. Which group of processes defines Project Scope Management?


A.
Initiation, Scope Planning, Scope Definition, Scope Verification, Scope Management
B. Scope Forecasting, Scope Definition, Scope Verification, Scope Control
C. Scope Planning, Scope Definition, Create WBS, Scope Verification, Scope Control
D. Scope Planning, Scope Description, Scope Verification, Integrated Change Control

Correct Answer: C