The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:
A. recognition and rewards B. compliance C. staff acquisition D. training needs
The zero duration of milestones in project planning occurs because milestones:
A. Are unpredictable and challenge the Plan Schedule Management process. B. Occur at random times in the project plans. C. Represent a moment in time such as a significant project point or event. D. Represent both significant and insignificant points in the project and are difficult to anticipate.