Project Management Professional (PMP) Exam Practice – Question0409 The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS: A. dictionary. B. chart. C. report. D. register. Show Answer Hide Answer Correct Answer: A