During a projects first planning meeting, the project team revised some requirements for parts and the manufacturers available for them. The team also revised delivery times and determined what parts could be made on site. After the meeting, the team created
a document to establish what, and how items should be procured from each vendor.
a document to establish what, and how items should be procured from each vendor.
What document did the team create?
A. Procurement statement of work (SOW)
B. Procurement management plan
C. Requirements management plan
D. Resource requirements