Project Management Professional (PMP) Exam Practice – Question1144

A project manager must evaluate and simulate the impact of a list of risks for a project's duration. What should the project manager do?


A.
Conduct a what-if scenario analysis.
B. Prepare a set of contingent response strategies.
C. Complete an expected monetary value (EMV) analysis.
D. Perform a schedule network analysis.

Correct Answer: A