Project Management Professional (PMP) Exam Practice – Question1282

A complex project is closing and many project team members report negative experiences. The project stakeholders from various areas of the organization may never work together again. As part of the project's requirements, the project manager must provide
lessons learned.
How should the project manager ensure this requirement is met?


A.
Document only the negative experiences so that alternative approaches can be developed for future projects.
B. Facilitate a session with the project team to review only positive experiences.
C. Reach out to each project stakeholder to capture their feedback on experiences from each phase of the project.
D. Initiate documentation of both the positive and negative experiences using the issue log and record of escalation.

Correct Answer: D