Your management has prescribed that a quality audit be conducted at the end of every phase in a project. This audit is part of the organization's______________
A. Quality assurance process
B. Quality control process
C. Quality improvement program
D. Process adjustment program
A. Quality assurance process
B. Quality control process
C. Quality improvement program
D. Process adjustment program