Your project management office implemented a project management methodology that emphasizes the importance of integrated change control. It states that change requests can occur in all the following forms EXCEPT______________


A.
Indirect
B. Legally mandated
C. Informal
D. Internally initiated

Correct Answer: C

Explanation:

Explanation:
Change requests are an input to the perform integrated change control process. Although occurring in many forms, they must be formal requests developed within the context of a change control system consisting of documented procedures.