Managing five contractors on your project for a new stadium in your City that can be used for baseball and for football and can be easily converted for either sport is a challenge along with managing your 15 person project team. You decided to conduct an audit of
one of your contractors and are______________


A.
Using it as a baseline for improvements to the other contracts under way
B. Verifying compliance in the seller's work processes
C. Accompanying it with a project quality audit
D. Using it for lessons learned documentation

Correct Answer: B

Explanation:

Explanation:
Inspections and audits are tools and techniques in the control procurements process. They are required by the buyer and supported by the seller in the procurement contracts and can be conducted as the project is executed to verify compliance in the seller’s
work processes or deliverables.