You are implementing a project management methodology for your company that requires you to establish a change control board. Which one of the following statements best describes a change control board?
A. Recommended for use on all (large and small) projects
B. Used to review, evaluate, approve, delay, or reject changes to the project
C. Managed by the project manager, who also serves as its secretary
D. Composed of key project team members
A. Recommended for use on all (large and small) projects
B. Used to review, evaluate, approve, delay, or reject changes to the project
C. Managed by the project manager, who also serves as its secretary
D. Composed of key project team members