An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs.
Which of the following actions should the project manager take?
A. Submit a new change request.
B. Initiate the regression plan.
C. Add remediation to the schedule.
D. Accept the new power output.