CompTIA Project+ PK0-004 – Question095

A program manager informs a project manager that a new, high-priority project has been approved and will need the current project's resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked.
Which of the following documents should the project team reference to fast-track the project? (Choose two.)

A.
Scope management plan
B. Configuration management plan
C. Network diagram
D. Project schedule
E. Project plan

Correct Answer: CD

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 171