CompTIA Project+ PK0-004 – Question203

When an action is taken on a risk, which of the following is being done and which document needs to be updated?

A.
Mitigating risk, and the risk register should be updated
B. Accepting risk, and the risk review document should be updated
C. Avoiding risk, and the risk review document should be updated
D. Exploiting risk, and the risk register should be updated.

Correct Answer: A