CompTIA Project+ PK0-004 – Question473

The government wants to start a project that will launch a satellite but lacks the appropriate SMEs. Which of the following would be BEST to solicit vendors?

A.
LOI
B. RFQ
C. RFI
D. SOW

Correct Answer: C