CompTIA Project+ PK0-004 – Question598

A project manager is reviewing a project's status and finds that while it is 25% under budget, there are significant quality defects, and the project is behind by six weeks.
Which of the following should the project manager increase to BEST resolve this issue?

A.
Resources
B. Quality
C. Schedule
D. Scope

Correct Answer: A

Explanation:

Explanation:
Resources on a project schedule typically refer to human resources and/or consulting or contracting resources who will work on the tasks.