CompTIA Project+ PK0-004 – Question599

Due to an overabundance of project issues reported at status meetings, a project manager wants to purchase a ticketing system to help manage the issues and impacts to the project.
Which of the following describes the information the new ticketing system would provide?

A.
RTM
B. KPIs
C. BAC
D. ETC

Correct Answer: B