A program manager informs a project manager that a new, high-priority project has been approved and will need the current project's resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked.
Which of the following documents should the project team reference to fast-track the project? (Choose two.)
A. Scope management plan
B. Configuration management plan
C. Network diagram
D. Project schedule
E. Project plan
Which of the following documents should the project team reference to fast-track the project? (Choose two.)
A. Scope management plan
B. Configuration management plan
C. Network diagram
D. Project schedule
E. Project plan