CompTIA Project+ PK0-004 – Question121

A part that is needed to complete Task 3 has been backordered and will arrive three days later than scheduled.
Task 3 must be complete for Task 4 to start. There is one day of float for the two tasks. Which of the following represents the number of days the project schedule will be delayed?

A.
Zero
B. One
C. Two
D. Three

Correct Answer: D