CompTIA Project+ PK0-004 – Question298

As a project processes, the team appears disjointed. Meetings are not effective because the right team members are not in the discussion, and functional managers are questioning if the project manager has a true management plan.
Which of the following documents should be reviewed FIRST to uncover the issue?

A.
Communications plan
B. Scope statement
C. Project management plan
D. Organizational chart

Correct Answer: A