CompTIA Project+ PK0-004 – Question325

Which of the following describes a project's budget overrun?

A.
The project spends only half of the funds.
B. The project spends only the allocated funds.
C. The project spends none of the funds.
D. The project spends in excess of the funds.

Correct Answer: D