CompTIA Project+ PK0-004 – Question378

Upon assignment to a project, the project manager is given a set budget, a due date, and a clearly defined description of desired deliverables. Which of the following should the project manager do NEXT?

A.
Create a Gantt chart of the milestones
B. Hold a kick-off meeting with the project team
C. Determine procurement needs to meet the project demands
D. Create the risk register

Correct Answer: C