A first-time project manager is developing a project charter.
Which of the following are key elements to have the project charter approved? (Choose two.)

A.
Project team
B. Business case
C. Detailed risks
D. Requirements
E. Service-level agreement
F. Detailed budget

Correct Answer: AB