CompTIA Project+ PK0-004 – Question600

Near the end of a sprint, the IT systems were taken down for a critical patch, and the team was inactive for four hours. The team members are concerned they will not be able to complete their tasks before the end of the sprint.
Which of the following BEST describes how the Scrum master should assist the team to finish on time?

A.
Bring the additional resources to help complete the work.
B. Add the uncompleted work to the product backlog.
C. Move the work to the next sprint.
D. Inform the team members they will need to work longer hours.

Correct Answer: A