CompTIA Project+ PK0-004 – Question601

A customer-requested project change has been approved, implemented, and validated.
Which of the following should the project manager do NEXT?

A.
Update the project charter.
B. Update the statement of work.
C. Update the lessons learned.
D. Update the project management plan.

Correct Answer: D