During a meeting, a new member of the PMO says, "If this project fails, then the portfolio fails, and the program as a whole ultimately fails."
Which of the following errors is the new PMO member making?
A. The new PMO member has not review the intra organizational strategy.
B. The new PMO member does not realize that although a project can fail, a program cannot, as it contains all projects in a company.
C. The new PMO member has confused the relationship between portfolio and program.
D. The new PMO member has not had an opportunity to review the company's project list.