CompTIA Project+ PK0-004 – Question645

A project manager failed to include quality testing in a software development project plan and must now add it while the project is underway.
Which of the following BEST describes the relationship that quality will have on the triple constraint?

A.
Time, cost, and scope will decrease.
B. Time and scope will remain static, and costs will increase.
C. Time and cost will increase, and scope will remain constant.
D. Time will remain static, and scope and costs will increase.

Correct Answer: C