CompTIA Project+ PK0-004 – Question707

A project manager decides to release a product one month later, knowing marketing studies have shown doing so could require increased manufacturing capacity. Which of the following risk strategies is being employed?

A.
Accept
B. Exploit
C. Transfer
D. Mitigate