In a functional organization, a project team member is known to be late on deliverables and regularly delays projects. A better resource is available but is not assigned to work on the project at this time. Which of the following strategies should be used to have the better resource assigned to the project?
A. Avoidance
B. Transference
C. Negotiation
D. Exploitation
A. Avoidance
B. Transference
C. Negotiation
D. Exploitation