CompTIA Project+ PK0-004 – Question678

A project manager is not receiving cooperation from a department that is vital to the success of a project.
Because of this, the project cannot move forward. Which of the following is the BEST place the project manager should go to get help with this issue?

A.
Project management office
B. Project stakeholders
C. Project team
D. Project sponsors

Correct Answer: A

CompTIA Project+ PK0-004 – Question677

A project has been created, and the project team has been identified. Which of the following is the NEXT step?

A.
Release an article on the company blog.
B. Conduct a company town hall.
C. Host a kickoff meeting.
D. Post a notice on social media.

Correct Answer: C

CompTIA Project+ PK0-004 – Question676

A homeowner wants to build a fence. It will take:
– A quarter of a day to measure the length of the fence
– Half a day to acquire the materials
– A quarter of a day to dig holes for the posts
– A quarter of a day to set the posts with concrete
– Two days for the concrete to dry
While the concrete is drying, the homeowner will spend a quarter of a day cutting the lateral pieces to size, half a day applying the coating to the remaining pieces, and then three days waiting for the coating to dry. It will then take the homeowner one day to assemble the fence. Which of the following is the length of time it will take the homeowner to build the fence?

A.
Six days
B. Seven days
C. Eight days
D. Nine days

Correct Answer: A

CompTIA Project+ PK0-004 – Question675

Input into a project's requirements is needed for clarification. With which of the following roles would the project manager MOST likely consult?

A.
Project risk manager
B. Project stakeholder
C. Project scheduler
D. Project coordinator

Correct Answer: B

CompTIA Project+ PK0-004 – Question674

A project manager has been receiving conflicting feedback from a variety of team members about the deliverables of another team member. The project manager sets up a mandatory team meeting to discuss the issue. Which of the following BEST describes this approach?

A.
Smoothing
B. Forcing
C. Negotiating
D. Confronting

CompTIA Project+ PK0-004 – Question673

A project manager identified a risk in a geographically unstable area. During the project, a volcano erupts, preventing project team access. Which of the following documents should the project manager update FIRST?

A.
Project schedule
B. Issue log
C. Risk register
D. Scope statement

Correct Answer: B