CompTIA Project+ PK0-004 – Question380

According to the communication management plan, the project scheduler is required to post weekly status reports on the project's intranet site. From the stakeholders' point of view, accessing the weekly report is an example of:

A.
interorganizational preferences
B. personal preferences
C. the interactive method
D. the pull method

Correct Answer: D

CompTIA Project+ PK0-004 – Question378

Upon assignment to a project, the project manager is given a set budget, a due date, and a clearly defined description of desired deliverables. Which of the following should the project manager do NEXT?

A.
Create a Gantt chart of the milestones
B. Hold a kick-off meeting with the project team
C. Determine procurement needs to meet the project demands
D. Create the risk register

Correct Answer: C

CompTIA Project+ PK0-004 – Question377

A project sponsor has requested documentation to determine the scheduled activities for a project that is running behind schedule. Which of the following documents should the project manager send to the sponsor to quickly identify the project activities?

A.
RACI
B. SWOT
C. SOW
D. WBS

Correct Answer: D

CompTIA Project+ PK0-004 – Question375

The PM has requested that a project repository be developed. Sensitive information will be available on the site that could affect the project's success. Only personnel who need to know the information will have access.
Which of the following site types is the PM requesting?

A.
Wiki page
B. Intranet
C. Extranet
D. Internet
E. Knowledge base

Correct Answer: A

CompTIA Project+ PK0-004 – Question374

A project manager has taken over a project that is already in progress. The project manager notices the functional manager of one team is unaware of the current progress. Which of the following should the project manager do? (Choose two.)

A.
Update the project charter to include the functional manager as a key stakeholder
B. Publish the project schedule to the functional manager
C. Review the communications plan to ensure proper involvement
D. Add the incident to the issue log and seek resolution
E. Ensure the functional manager is on the status report distribution list

Correct Answer: AC

CompTIA Project+ PK0-004 – Question372

In the review of a project status report, the slack is negative. Which of the following should the project manager tell the stakeholders?

A.
The project is behind schedule
B. The project is over budget
C. The project has float available
D. The project needs a gate review

Correct Answer: A

CompTIA Project+ PK0-004 – Question371

The PMO is confused by an entry in the risk register and would like the project manager to provide clarification regarding strategy. Based on the following entry:

Which of the following should be modified to BEST eliminate confusion?

A.
Change the status to issue and include it in the issue log
B. Change the strategy to mitigate
C. Change the name to identify the problem clearly
D. Change the owner to sponsor

Correct Answer: B