Project Management Professional (PMP) Exam Practice – Question0817

A company notices that, during the last six projects, the scope changed substantially. What should the project manager of a new project do first to reduce the likelihood of scope changes?


A.
Ask for managements guidance.
B. Review lessons learned from the previous projects.
C. Review the project scope statement.
D. Plan to mitigate the impact of scope change.

Correct Answer: B