CompTIA Project+ PK0-004 – Question602

A project manager arrives at a worksite and finds the installation team performing unapproved work. The installation team claims the sponsor verbally requested the work, as it was necessary for the project.
Which of the following has MOST likely occurred?

A.
Scope creep
B. Gold plating
C. Task reprioritization
D. Lack of requirements

Correct Answer: A

Explanation:

Explanation:
Scope creep involves changing the project or product scope without having approval to do so and without considering the impacts that will have on the project schedule, budget, and resources.