CompTIA Project+ PK0-004 – Question130

A governance committee has just approved a new project. The project scheduler is now developing the project schedule. Which of the following activities should be done FIRST?

A.
Add durations.
B. Add the start and finish dates
C. Add tasks.
D. Add resources.

Correct Answer: C

CompTIA Project+ PK0-004 – Question128

During a project, a key stakeholder asks a project team member to add a requirement. The team member adds the requirement without informing the project manager. Which of the following is described in this scenario?

A.
Change request
B. Risk mitigation
C. Change control
D. Scope creep

Correct Answer: D

CompTIA Project+ PK0-004 – Question126

A project manager has been assigned a complex project and does not know all the activities required to complete it.
Which of the following if the BEST approach to determine the work packages for the WBS?

A.
Brainstorming
B. Analogous
C. Bottom-up
D. Forward pass

Correct Answer: C

CompTIA Project+ PK0-004 – Question124

A project manager travels abroad to meet the offshore team and sends out a meeting invitation to review requirements. However, many team members decline the meeting invitation. The PM approaches one team member to determine why people are declining. The team member indicates the project manager scheduled the meeting at a time when employees typically have permission to take a nap. Which of the following is the project manager facing?

A.
Language barriers
B. Time zones
C. Cultural differences
D. Personal preferences

Correct Answer: C

CompTIA Project+ PK0-004 – Question123

A team member learns that an assigned task is not due until the very end of the project. Moreover, the team member is not aware of any predecessor tasks dependent on completing the assigned task. Which of the following does the project manager use to decide if the team member can start the task later or earlier?

A.
Review the PERT chart and evaluate if the task is a critical dependency.
B. Review the PERT chart and evaluate if the task is a discretionary dependency.
C. Review the PERT chart and evaluate if the task is a real dependency.
D. Review the PERT chart and evaluate if the task is an external dependency.

Correct Answer: B

CompTIA Project+ PK0-004 – Question122

A software development project is struggling with a certain technology that is unknown to the project team. A project manager has received a third-party proposal to transfer the risk. Which of the following should the project manager do NEXT?

A.
RF1
B. RFP
C. RFQ
D. Change request
E. Request for bid

Correct Answer: E

CompTIA Project+ PK0-004 – Question121

A part that is needed to complete Task 3 has been backordered and will arrive three days later than scheduled.
Task 3 must be complete for Task 4 to start. There is one day of float for the two tasks. Which of the following represents the number of days the project schedule will be delayed?

A.
Zero
B. One
C. Two
D. Three

Correct Answer: D