CompTIA Project+ PK0-004 – Question600

Near the end of a sprint, the IT systems were taken down for a critical patch, and the team was inactive for four hours. The team members are concerned they will not be able to complete their tasks before the end of the sprint.
Which of the following BEST describes how the Scrum master should assist the team to finish on time?

A.
Bring the additional resources to help complete the work.
B. Add the uncompleted work to the product backlog.
C. Move the work to the next sprint.
D. Inform the team members they will need to work longer hours.

Correct Answer: A

CompTIA Project+ PK0-004 – Question599

Due to an overabundance of project issues reported at status meetings, a project manager wants to purchase a ticketing system to help manage the issues and impacts to the project.
Which of the following describes the information the new ticketing system would provide?

A.
RTM
B. KPIs
C. BAC
D. ETC

Correct Answer: B

CompTIA Project+ PK0-004 – Question598

A project manager is reviewing a project's status and finds that while it is 25% under budget, there are significant quality defects, and the project is behind by six weeks.
Which of the following should the project manager increase to BEST resolve this issue?

A.
Resources
B. Quality
C. Schedule
D. Scope

Correct Answer: A

Explanation:

Explanation:
Resources on a project schedule typically refer to human resources and/or consulting or contracting resources who will work on the tasks.

CompTIA Project+ PK0-004 – Question596

A project team has just implemented an approved change to a project.
Which of the following should occur NEXT?

A.
Validate the change.
B. Evaluate the impact of the change.
C. Implement a regression plan.
D. Update the issue log.

Correct Answer: B

CompTIA Project+ PK0-004 – Question595

While working on a project, a self-organized team determines what will be accomplished during the next two weeks.
Which of the following describes what the team is doing?

A.
Creating a WBS
B. Gathering continuous requirements
C. Sprint planning
D. Holding a Scrum meeting

Correct Answer: C

Explanation:

Explanation:
A sprint, which is a time-bound period of work, always starts with a sprint planning meeting. During the meeting, team members choose items from the backlog to work on during the sprint. The backlog is a list of requirements (both functional and nonfunctional) for the project. The product owner prioritizes the backlog items based on business need, risk, and value to the organization. The Scrum team members break down large requirements into manageable portions of work that can be completed in a sprint.

CompTIA Project+ PK0-004 – Question594

A first-time project manager is developing a project charter.
Which of the following are key elements to have the project charter approved? (Choose two.)

A.
Project team
B. Business case
C. Detailed risks
D. Requirements
E. Service-level agreement
F. Detailed budget

Correct Answer: AB

CompTIA Project+ PK0-004 – Question593

A customer-requested change has been denied by the CCB.
Which of the following should the project manager do NEXT?

A.
Halt project work until a meeting with the customer and the project sponsor takes place.
B. Update the project issues log.
C. Report the denied request to the customer and proceed with project work.
D. Reestablish the project baselines.

Correct Answer: C

CompTIA Project+ PK0-004 – Question592

An organization recently restructured. Leaders feel they are not in a position to sign off on a required change, which is delaying a project.
Which of the following is the obstacle?

A.
Ability to identify approval authority
B. Incomplete change control documentation
C. Project team autonomy
D. Change validation process

Correct Answer: D