CompTIA Project+ PK0-004 – Question610

A project to implement Voice over Internet Protocol for a contact center has been expanded to include the entire organization.
Which of the following BEST describes the constraints involved?

A.
Deliverables, schedule, and resources
B. Stakeholders, scope, and schedule
C. Schedule, quality, and deliverables
D. Resources, requirements, and scope

Correct Answer: B

CompTIA Project+ PK0-004 – Question609

During a weekly meeting, a project manager mentioned a decision was made on June 17 to include future state workflows in onboard training.
Which of the following communication methods should be used?

A.
Project communications plan
B. Project dashboard
C. Project schedule
D. Project status report

Correct Answer: D

CompTIA Project+ PK0-004 – Question607

A project manager wants to determine the percentage of a project's budgeted costs versus expenditures.
Which of the following calculations should the project manager perform?

A.
Burn rate
B. Critical path analysis
C. EV
D. EAC

Correct Answer: A

Explanation:

Explanation:
Expenditure tracking includes measuring the project spending to date, determining the burn rate (or how fast you’re going through the money), and tracking expenditures to the cost baseline so that stakeholders can see what was planned versus what was actually spent on the project.

CompTIA Project+ PK0-004 – Question606

Which of the following is MOST commonly associated with the WBS and used to develop a project timeline?

A.
Process diagram
B. RACI matrix
C. Gantt chart
D. Network diagram

Correct Answer: C

Explanation:

Explanation:
Gantt charts can show milestones, deliverables, and all the activities of the project including their durations, start and end dates, and the resources assigned to the task. Gantt charts typically display the tasks using a horizontal bar chart format across a timeline. I know project managers who have constructed Gantt charts for small projects using only a spreadsheet.

CompTIA Project+ PK0-004 – Question605

A project team decides to obtain a support contact on one of the hardware infrastructures being used on the project. This is to ensure the project is grounded if an issue with the hardware occurs during the course of the project.
This type of risk response is known as:

A.
mitigation.
B. avoidance.
C. transference.
D. acceptance.

Correct Answer: A

Explanation:

Explanation:
You’ll use several strategies when determining both negative risks and opportunities and formulating your response plans. The strategies to deal with negative risks include the following:
– Avoid: Avoiding the risk altogether or eliminating the cause of the risk event
– Transfer: Moving the liability for the risk to a third party by purchasing insurance, performance bonds, and so on
– Mitigate: Reducing the impact or the probability of the risk
– Accept: Choosing to accept the consequences of the risk

CompTIA Project+ PK0-004 – Question604

Top-level managers are considering joining certain projects, programs, and operations to be managed as a group.
Which of the following is being considered?

A.
Organizational changes
B. PMO establishments
C. Project interdependencies
D. Program development

Correct Answer: C

CompTIA Project+ PK0-004 – Question603

In a highway construction project, the project team has identified the need to utilize additional land for staging equipment.
After documenting the change request, which of the following should be accomplished NEXT?

A.
Communicate with the stakeholders
B. Audit the documentation
C. Obtain approval
D. Identify the approval authority

Correct Answer: D

CompTIA Project+ PK0-004 – Question602

A project manager arrives at a worksite and finds the installation team performing unapproved work. The installation team claims the sponsor verbally requested the work, as it was necessary for the project.
Which of the following has MOST likely occurred?

A.
Scope creep
B. Gold plating
C. Task reprioritization
D. Lack of requirements

Correct Answer: A

Explanation:

Explanation:
Scope creep involves changing the project or product scope without having approval to do so and without considering the impacts that will have on the project schedule, budget, and resources.

CompTIA Project+ PK0-004 – Question601

A customer-requested project change has been approved, implemented, and validated.
Which of the following should the project manager do NEXT?

A.
Update the project charter.
B. Update the statement of work.
C. Update the lessons learned.
D. Update the project management plan.

Correct Answer: D